About the Customer

Company: Apollo, Inc.

Location: Richland, Washington

Project Overview

  • 772′ (235m) long up to 79′ (24m) tall from the top of the drilled shaft to the roadway
  • 2 phases:
    • Phase 1: 6 piers
    • Phase 2: Pier located over the Yakima River

Project Requirements

  • Architecturally sound walls
  • Patterning of vitae in the concrete
  • Granite pillars in the walls
  • Steep hillside over the river made it difficult to access

Formwork Used

PLATE GIRDER®

E-Z DECK®

Customer Benefits

  • Self-spanning system
  • 250 kip support brackets support tireless system forming pier cap

From EFCO’s management/engineering staff to the field supervisor, they were always accommodating to our schedule for submittals, material procurement, and installation guidance. Our team encountered a challenge at pier 3, Dennis and the EFCO team were very responsive to collaborate with our crews to mitigate schedule impacts and provide a resolution for all parties. We keep using EFCO products because they are fast, high production, easy to cycle and user-friendly.

– Brett Brown, Apollo Project Manager

Duportail/Stevens Corridor Development - Richland, Washington
Duportail/Stevens Corridor Development - Richland, Washington
Duportail/Stevens Corridor Development - Richland, Washington
Duportail/Stevens Corridor Development - Richland, Washington
Duportail/Stevens Corridor Development - Richland, Washington
Duportail/Stevens Corridor Development - Richland, Washington
previous arrow
next arrow
Slider

REQUEST INFORMATION