About the Customer

Kings Construction Company Logo

Company: Kings Construction

Project Location: Wichita, Kansas

Project Requirements

  • The first bridge consisted of single-column piers with hammerhead caps. These 4′-6″ x 4′-6″ (1.4 m x 1.4 m) piers ranged in height from 41′-6″ to 47′ (12.6 m to 14.3 m) tall.
  • The second bridge contained two- and three-column piers. The pier caps spanned over all of the columns. The pier caps were 4′-6″ wide x 4′-6″ tall (1.4 m x 1.4 m) and ranged in length from 22′-7″ to 31′-4″ (6.9 m to 9.6 m).
  • All of the pier caps required the use of a brick pattern form liner that was attached directly to the steel face of the form.

Formwork Used

PLATE GIRDER®

Round Column®

Project Overview

The project addressed several of the heaviest traffic movements between I-235 and U.S. 54/400 running east and west through Wichita, Kansas.

 

Customer Benefit

  • Hands-on training with the EFCO PLATE GIRDER® at EFCO’s Concrete Construction and Forming Institute
  • Using the Self-Spanning PLATE GIRDER® system, the pier forms were bolted together on the ground with the EFCO Quick Bolt® and hoisted into place in two picks.
  • The EFCO steel form delivers the highest quality concrete finish.
Red Highway Improvement Project in Wichita, Kansas
Red Highway Improvement Project in Wichita, Kansas
Red Highway Improvement Project in Wichita, Kansas
Red Highway Improvement Project in Wichita, Kansas
previous arrow