About the Customer

North America Construction (1993) LTD Logo

Company: North America Construction (1993) LTD.

Project Location: Township of Langley, BC, Canada

Project Requirements

  • 30′ (9 m) tall exterior walls which tilt 5 degrees inward
  • Installing 9′-7 3/16″ (2.9 m) wide form liners to almost the full wall height that do not allow for tie penetration
  • This site-specific modular design kept the tie spacing to a very specific location that complemented the architectural finish requirement

Formwork Used

PLATE GIRDER

Project Overview

Phase 1 of the project involves the construction of a dual cell, 5.4 MGal (20.6ML) reinforced concrete potable water reservoir, and a main valve control chamber. The reservoir is an above ground structure which will have a community park on the roof to allow the residents of the nearby communities to enjoy the space.

 

Customer Benefits

  • EFCO’s PLATE GIRDER with varying heights, as well as a specially designed tie panel
  • The contractor was able to span across the form liners and transfer the 9′-7 3/16″ (2.9 m) wide x 30′ (9 m) tall load to ties installed on the sides of the liner
Jericho Reservoir – Township of Langley, BC, Canada
Jericho Reservoir – Township of Langley, BC, Canada
Jericho Reservoir – Township of Langley, BC, Canada