Lima Metro Line 2
About the Customer
Company: Consorcio Linea 2 Metro Lima
Location: Lima, Peru
Project Overview
Tunnel east-to-west 82′ (25m) below the city for 16.8 miles (27km) and contains 27 stations.
Project Requirements
- Open pit tunnel straight and curved areas
- 2 stages
- First stage, gable walls total length 1,640′ (500 m)
- Second Stage – 3,660 yd³ (2,800 m³) of concrete to create the 492′ (150 m) long crown
Formwork Used
Customer Benefits
- The PLATE GIRDERS® created a beam that allowed the 16.5 ton (15 tonne) traveler to be supported and moved on rollers
Several problems were faced during the construction process, but with the help of EFCO’s Field Service and EFCO’s Engineering Department, they were successfully solved and kept us moving forward productively. Thanks to the commitment of EFCO’s team and the excellent service provided for the solution and improvement of the project, our civil engineers were extremely pleased and are looking forward to partnering with EFCO on future projects.
– Edward Cuba, Production Engineer