Newark Liberty International Airport – Terminal One Redevelopment
Project Requirements
- N61 is approximately 895 feet long
- N62 is approximately 660 feet long
- N63 is approximately 850 feet long.
- The curved structures include 13 pier caps along with abutments and wingwalls
Formwork Used
Project Overview
Three bridge structures: N61, N62 and N63, all with abutments, wingwalls and piers.
Customer Benefits
- When working on the pier caps, their first thought was to construct with the typical design of PLATE GIRDER® sides and soffit, but were faced with the challenge of complex rebar issues
- Using E-Z DECK® for the support and work platform along with PLATE GIRDER side forms
- Conti’s crew was able to cycle the shoring and side forms with minimal breakdown. This allowed them to improve labor productivity and ultimately stay on production schedule