Hearthstone Storm Drain Improvement Project
Project Requirements
- 52′ (15.8 m) long Box Traveler to pour 50′ (15 m) long typical sections at a rapid pace
- 12′ (3600 mm) W x 8′ (2400 mm) H double-barrel Box Traveler that would convert to two single barrel systems
Formwork Used
EFCO Box Traveler®
EFCO LITE®
Project Overview
The Hearthstone Storm Drain Improvement included the construction of a 2,000′ (610 m) channel for drainage in Filmore, Califorina.
Customer Benefits
- A crew of 4-5 carpenters can easily cycle it every other day, while it is not uncommon to pour every day if the invert and iron workers can keep up with the pace
- Box Traveler system can be converted to a single-barrel system by adding exterior wall gangs
- EFCO LITE® soffit panels can be easily added or removed to change the width of the system