About the Customer

Company: IAQ SOLUTION SDN. BHD. JV CCIE ENGINEERING SDN BHD

Project Location: Sungai Kapar Indah, Klang, Selangor, Malaysia

Formwork Specialist – Malaysia

Stephen Koon, EFCO-Malaysia Territory Manager
Foo Ming Huang, EFCO-Malaysia Field Supervisor
Kevin Khor, EFCO-Malaysia Engineer

Project Requirements

Formwork For Three-Story Concrete Column Construction.

PLATE GIRDER® column formwork 3′-6″ x 3′-6″ modifiable to 3′ x 3′ (1000 mm x 1000 mm modifiable to 900 mm x 900 mm)

EFCO LITE® column formwork 24″ – 32″ x 24″ – 32″ (600 mm – 800 mm x 600 mm x 800 mm)

EFCO LITE column formwork 10″ – 16″ x 10″ – 16″ (250 mm – 450 mm x 250 mm – 450 mm)

Vertical Stacked Shoring

E-Z DECK® shoring system with an estimated 35,520 ft² (3,300 m²)per each floor

Formwork Used

PLATE GIRDER®

EFCO LITE®

E-Z DECK®

Project Overview

The Vital Healthcare: Industrial Development is a three-block, three-story factory with a warehouse and office. Once completed, the factory will have 80,730 ft2 (7,500 m2) of floor area equipped with a production floor, finished goods warehouse with loading docks, semi-trailer parking bays and a guard house.

Customer Benefits

Experienced Formwork and Shoring Company

EFCO, Why Choose anyone else?

Concrete Formwork For Walls And Columns

EFCO’s PLATE GIRDER and EFCO LITE column formwork is easy to install, because it does not require concrete form ties. This eliminates the need to go back and patch tie holes.

Reduces The Need Of Dismantling Formwork And Optimizes Construction Costs

EFCO column formwork can be easily lifted in an L-Shaped orientation in one crane pick with the attached EFCO Heavy-Duty Pipe Braces.

Simple, Fast Vertical Stacked Shoring

The lightweight E-Z DECK shoring equipment is cycled horizontally and cycled six times to complete the three blocks.

Maximum Safety In Load Bearing Tower

EFCO’s E-Z DECK® system has an advantage over other systems as it only needs to be assembled once, and its height adjustment is easily done by turning the jacks up or down, even under high loads.

Versatile Shoring System For Slab & Beam Construction

Placing the lightweight E-Z DECK modules on EFCO’s Crazy Wheel Dollies which are then easily pushed by workers to the next casting zone.

Easy Shoring System Installation

E-Z DECK Panel, is easily installed with a hammer and does not require any other accessories.

Lowest in-place concrete cost, saving time and cost for the customer

The Vital Healthcare: Industrial Development, Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development
Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development, Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development
Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development, Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development
Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development, Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development
Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development, Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development
Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development, Sungai Kapar Indah, Klang, Selangor, Malaysia
The Vital Healthcare: Industrial Development
Sungai Kapar Indah, Klang, Selangor, Malaysia
previous arrow
next arrow