Demonstrating Leadership in Precast and Cast-in-Place Concrete Construction

York, Pennsylvania

100-Year-old Dam Rebuild Project

The Lake Williams Dam Rehabilitation project in York, Pennsylvania, is a multi-year project involving the restoration of a century-old dam, spillway, bridge, and utilities initially constructed in 1911. This $40 million project aims to ensure the dam’s continued structural integrity, aligning it with current regulations and design safety standards. The York Water Company contracted with Kinsley Construction to demolish most of the old dam and construct the new dam structures.

Meeting Unique Challenges Head-On

This project presented unique challenges for Kinsley Construction, marking their first venture into Roller Compacted Concrete (RCC) construction. Effective communication between Kinsley’s teams and EFCO led to innovative formwork designs that minimized reassembly by cycling large gangs, resulting in efficient cycle times for the placement of the RCC.

High-Quality, Steel-Faced Formwork Solution

The lake levels were lowered 20′ (6.1 m) below full to allow Kinsley to start construction on the pipe encasement that was topped with Roller-Compacted Concrete. The pipe encasement stretched approximately 180 LF (55 m). This structure’s origin is upstream from the intake structure, flows through the intake tower, and continues another 150′ (46 m) downstream to the principal spillway. To form and support the 1′ (300 mm) RCC lifts of the lower pours atop the encasement, EFCO PLATE GIRDER® panels were ganged together with cantilevered SUPER STUD® stiffbacks and cycled vertically as the encasement grew in height. The initial lift was 180′ (55 m) in length; with minimal adjustments, the panels were able to be used for each subsequent lift, with the final lift being 17’-6″ (5.3 m) long. These gangs, which were 8′ (2.4 m) in height, were easily cycled in 24′ (7.3 m) long picks and re-used.

Efficiency in Principal Spillway Construction

To construct the principal spillway, Kinsley Construction used precast panels for the dam’s upstream face, and PLATE GIRDER formwork for the gravity walls. EFCO engineer, John Lust, designed a SUPER STUD frame system for the precast panels, providing the necessary support and allowing the RCC to be placed against the precast panels.

Why Kinsley Chose EFCO

EFCO provided an Innovative formwork solution with large panels maximizing surface coverage and strategically placing joints for efficient cycling. This approach involved upfront consultation with the Kinsley team and ongoing field service support through site visits, ensuring the lowest in-place concrete costs and adherence to best practices. The combined effort and expertise of Kinsley Construction and EFCO resulted in the successful rehabilitation of the century-old Lake Williams Dam, ensuring its continued service for generations to come.

 

Thank you for your help and outstanding customer service! Honestly, I’ve used every formwork supplier, and by far, you are the best with tech support and prompt responses.

- Chris Kotchish, Superintendent

EFCO EQUIPMENT

PLATE GIRDER

SUPER STUD

E-BEAM®

 

Contact our Pittsburgh office today

203 S. Duffy Road

Butler, PA 16001

Phone: (614) 876-1226

 

Download PDF

Kinsley Construction TEAM

Rich Diehl, Project Manager

Scott Prowell, Project Manager

Chris Kotchish, Superintendent

Max Klinefelter, Superintendent

Terry Harlacker, Superintendent

Edgar Aguilar, Project Engineer

 

EFCO FORMWORK SPECIALISTS–Pittsburgh

Zac Boda, Territory Manager

Rick Lynch, Field Supervisor

John Lust, Engineer

Project Photos

Trusted Formwork Partner

Why Trust Anyone Else?

We are ready to assist you in finding the best forming and shoring solutions for your construction projects. 

Contact Us Today! 

Why Trust Anyone Else but EFCO