Lusaran Bulk Water Supply | Cebu City, Philippines
Water Treatment Plant, One Formwork Supplier
Cebu City, Philippines
Formwork Supplier for Strict Construction Timeline
Billions of people worldwide lack access to clean water, with many locations facing challenges in providing safe drinking water. In Cebu City, Philippines, contractor JE Hydro & Bio-Energy Corp. is not only the contractor of this project but also the developer that is helping to provide stable potable water daily in at least nine Cebu City mountain villages. EFCO was the formwork supplier solution that allowed the contractor to pour concrete for the Lusaran Bulk Water Supply Project safely and quickly while keeping the construction project on a strict timeline.
Growing Economy Requires Water Treatment Plant
Despite the growing economy, the Philippines faces significant challenges in terms of water and sanitation access. JE Hydro, a fully Filipino-owned company, has completed the construction of this water treatment plant, which will augment the potable water supply of the Metropolitan Cebu Water District (MCWD).
New Construction of Water Treatment Plant
The new construction of the water treatment plant has one of the lowest power usage rates within the WTP battery limit, maintains a zero-effluent discharge operation, and utilizes the most efficient filtration system (JE-Underdrain + Activated Filter Media) available. It provides an additional twenty (20) million liters per day of drinking water. This 1.1B peso project is estimated to serve 40,000 households or 200,000 individuals in the MCWD Reservoir at Barangay Busay in Cebu.
150-day Handset Formwork Solution
JE Hydro partnered with EFCO because they needed a handset formwork solution to meet the aggressive construction schedule of 150 days to complete the structure from groundbreaking to commissioning.
Cast-In-Place Handset Formwork
Consultation and professional support helped the JE Hydro team choose the best-suited cast-in-place formwork for this project. EFCO’s handset formwork system, HAND-E-FORM®, was the formwork used to form all the tank structures.
Monolithically Poured Concrete
The construction of the Sedimentation Tank utilized 3,000 m2 of the EFCO HAND-E-FORM system. The concrete was poured monolithically into the formwork at 3 m tall. The operation required a constant cast-in-place schedule comprised of 40 concrete trucks.
Formwork Partner for Sand Filter Tanks
To eliminate unplanned costs and delays, JE Hydro partmered with EFCO through every step of the project. The Rapid Sand Filter Tank required less formwork and was constructed using lifts and slabs. JE Hydro used the formwork efficiently and to its fullest capacity.
EFCO EQUIPMENT
EFCO FORMWORK SPECIALISTS–PHILIPPINES
Reneil Jopia, Territory Manager
Ferdinand Castro, Field Supervisor
Abunasif Gubat, Field Supervisor
Jeanna Fernandez, Engineer
JE Hydro & Bio-Energy TEAM
Joffrey Hapitan, Chairman & CEO
Steffi Hapitan, Comptroller
Karl Gajudo, Project Engineer
The JE Hydro Water Treatment Facility in Barangay Lusaran, Cebu City, is one of the most versatile water treatment plants to be constructed in the Philippines.
-Joffrey Hapitan, Chairman & CEO of JE Hydro
EFCO’s HAND-E-FORM® system has proven to be the most efficient and flexible formwork system we have used during the civil construction phase of our project. The response and assistance provided by EFCO in planning and implementation are the key benefits that have helped us remain cost-effective and on schedule.
-Steffi Hapitan, Comptroller